Pottery Road update

Torontonians will recognize Pottery Road as the space warp that gets them from the Bayview Extension to Broadview Avenue north of Danforth. As such, it takes a lot of pressure off other arteries to and from downtown, such as the  big bridge (the Princes’ Viaduct) over the Don Valley Parkway. It’s an old road that winds down a steep hill, ducks under the Don Valley Parkway, and  crosses the Don River via an old cement bridge. This summer the city undertook to improve the road and sidewalk and install street lights. It was supposed to open September 7th.

Pottery Road in the Don Valley

I hope you haven’t been holding your breath.

It didn’t open on time. It was going to open September 30.

I hope you weren’t holding your breath.

The latest is that the hillside above the road is safe but not up to safety standards. I’m not sure which retaining wall  they’re talking about since most of the north side of the road is natural slope. Did I mention that someone just built an apartment building looming over the road? Regardless, the engineers aren’t satisfied and they’re taking measurements and considering what to do.

“The wall is safe…but, it’s not within acceptable engineering limits,” said Gord MacMillan, director of design and construction for the City of Toronto.

Here’s the update. I think they’ll be finished about February. What do you think?

 The City’s design consultants have been working on an engineering solution to increase the stability of the embankment above the newly constructed retaining wall on the north side of Pottery Rd, east of the Don Valley Parkway which remains the sole reason for the continued road closure.   

 On the basis of engineering designs prepared by the consultant, Technical Services is in the process of obtaining price quotations and realistic construction timelines. The General Contractor’s sub-contractors are expected to submit quotations and construction schedules by October 7th 2011.

Unfortunately, we still do not have a date for the re-opening of Pottery Road

Advertisements

2 Responses to “Pottery Road update”

  1. clutchmillsie Says:

    douchebags…they were inconsiderate enough to shut down the eastbound gerrard st bridge too..all summer both were closed..Great work city of toronto..really made it easy for riverdale and east york taxpayers to get home


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: